Delivering the AMP5 Capital programme – don’t be caught out by over precautionary mitigation

Designing cross country pipelines to avoid ecological impact is key to successful capital project delivery. Failure to manage ecological risks from the outset can add significant cost and time to a project. Implementing excessive mitigation can make things even worse.

Jonathan Taylor, who has recently joined ADAS as Regional Ecologist from Thames Water, has had considerable experience in managing and advising on the ecological impact of pipeline construction. “Very often ecological consultants who are not used to pipeline construction don’t always completely understand the differences between the temporary nature of the ecological impact as opposed to permanent development”, comments Jonathan. “Mitigation strategies should be developed that are proportional to the impact – if that impact is temporary – then the mitigation should be designed to reflect that”.

In many situations the methodologies proposed for temporary habitat disturbance are more appropriate for where permanent habitat loss is envisaged – the result being invasive and disproportional mitigation which in extreme cases can cause more impact than the work itself.

Most work for Ecological Consultancies involves the mitigation of permanent impact, be that the construction of housing developments or infrastructure schemes. It takes a different set of skills and understanding to mitigate the impact of pipeline construction, where an understanding of habitat reinstatement and restoration are crucial.

Jonathan, who started out as an engineer, also understands construction methods that are used. “There is a big variation in the impact different machines and working methods can have” he says. “The important thing is to understand this, so you can work to lower the impact as much as possible”. Understanding the construction activities, opens up a variety of techniques that can be used to manage and mitigate ecological impact, such as using no dig techniques and enhanced soil handling techniques. Working closely with the main contractor on site is a vital component to this.

ADAS have considerable experience of working with the Water Industry and other utilities to devise ecological mitigation methodologies that are proportional and pragmatic, meeting the needs of our clients, and the needs of the Regulators. We have worked with many of the main contractors employed to deliver complex capital projects and are regularly successful in avoiding ecological impact during the design stages of a project. As a result, we provide a service that is right for the client, achieves first time, and is based on sensible and balanced solutions.

For more information please contact call Jonathan Taylor on 01235 438 900 or email: jonathan.taylor@adas.co.uk

OTHER WATER ARTICLES

Screening tool central to flood risk assessment
27 February 2009

Screening tool central to flood risk assessment

The increasing frequency of potentially catastrophic flooding events has focused the attention of utility companies on flood risk assessment for those installations vital in maintaining customer supplies. ADAS has developed...

Flooded with information
02 March 2009

Flooded with information

The floods of the summer of 2007 had impacts on arable, horticultural and livestock farming and food production across the UK. ADAS delivered intelligence to Defra on a daily...

NVZ solutions delivered
02 March 2009

NVZ solutions delivered

New rules are in place which relate to the way that farmers need to manage their land, in particular the management of Nitrogen within Nitrate Vulnerable Zones. ADAS staff...

Water Concerns Conference highlights need for catchment solutions
06 April 2009

Water Concerns Conference highlights need for catchment solutions

Catchment management plans will be vital if the UK is to improve water quality and reduce its greenhouse gas emissions, according to scientists from ADAS speaking at the consultancy’s Water...

NVZ regulations bring business plans into focus for dairy farmers
08 April 2009

NVZ regulations bring business plans into focus for dairy farmers

Following new environmental regulations which came into force on the 1st January 2009, dairy farmers are having to reassess business plans in order to maximise their resources.